The construction efforts for Unity Park remain ongoing, with the month of May proving to be a period of heightened activity.
Stage 3
We are thrilled to advise that Stage 3 Titles registered on 14 April 2023. Settlements are expected to follow in late April 2023.
Stage 4
Footpath paving works nearing completion with topsoiling anticipated to commence in late April 2023.
Stage 4 Anticipated Settlement Date: mid-2023
Stage 5
Electrical and communications reticulation complete with footpath paving works well underway.
Stage 5 Anticipated Settlement Date: mid-2023
Stage 6
Pavement construction commenced in April 2023. Water reticulation is expected to start in May 2023.
Stage 6 Anticipated Settlement Date: Q3 2023
Stage 7
Drainage works underway with pavement construction to commence in May 2023.
Stage 7 Anticipated Settlement Date: Q4 2023